Municipal ENGINEERING OFFICE
SERVICES
1. Issuance of Building Permit
-
Who may avail: Building owner / applicant
-
Requirements:
-
Zoning permit/clearance
-
DOLE certification/clearance
-
Accomplished application form (signed/sealed by licensed engineer/architect)
-
5 sets of signed/sealed plans
-
Land title / deed of sale / deed of donation
-
Vicinity map (signed/sealed by geodetic engineer)
-
Structural design (for 2-storey & above)
-
Bill of materials & cost estimates
-
Specifications
-
-
Steps: Secure and submit forms & plans → Site inspection & evaluation → Endorse to BFP/DOLE → Pay fees → Receive permit
-
Fee: Based on PD 1096 (National Building Code), DPWH MC 1 s.2004, and Fire Code of the Philippines
-
Processing Time: 4 days & 1 hour
2. Issuance of Occupancy Permit
-
Who may avail: Building owner / applicant
-
Requirements:
-
Fire Department certification
-
As-built plan (signed/sealed by licensed engineer)
-
Logbook
-
-
Steps: Secure form → Submit plans & requirements → Pay fees → Processing & approval → Receive occupancy permit
-
Fee: Occupancy permit fee (per PD 1096 and DPWH MC 1 s.2004)
-
Processing Time: 3 hours
3. Issuance of Electrical Permit
-
Who may avail: Building owner / applicant
-
Requirements:
-
Zoning certification
-
Fire Department electrical connection certification
-
Electrical layout (signed by Professional Electrical Engineer)
-
-
Steps: Submit layout & requirements → Assessment & inspection → Endorse to BFP → Pay fees → Receive electrical permit
-
Fee: Electrical permit fee (per PD 1096 and DPWH MC 1 s.2004)
-
Processing Time: 1 day & 1 hour